New milestone crossed for newbuild Stampede platform in US Gulf on way to first oil

Author: Kathrine Schmidt
26 Jul 2017 19:31 GMT Updated 1 Aug 2017

Hess has ticked off another milestone in its progress to first oil at the Stampede development in the US Gulf of Mexico, having completed installation of its tension-leg platform offshore, the company said.

The US independent also said hookup activities had begun for the development in Green Canyon Blocks 468, 511 and 512, an update shared along with quarterly earnings on Wednesday.

"One well has been drilled and completed, and completion operations are underway on the second and third wells," Hess said in a statement.

"First production from the field is expected in the first half of 2018."

The TLP will have capacity for some 80,000 barrels of oil per day, with resources estimated at 300 million to 350 million barrels of oil equivalent.

Hess operates with a 25% stake, with partners Chevron, Statoil and CNOOC also on a quarter each.

The Stampede process has now passed the stage where the last tension-leg platform installation in the US Gulf -- Chevron's Big Foot -- floundered in 2015. 

Some of the tendons -- which attach the platform to the seafloor for stability -- on that project were irreparably damaged after a failure of buoyancy modules. 

After the tendons were installed, the flotation devices were supposed to hold the tethers at the ready as the setup awaited installation of the platform. But, some detached, leaving the tendons to fall, irreparably damaging and forcing re-fabrication of some of them.

The US supermajor has recovered an insurance claim and reached an out of court settlement with a contractor. That development, too, is planned for first oil in 2018 but in the latter months.

Reprinted with permission.

Related News
  • Hess Announces Significant Reduction to 2020 Capital and Exploratory Budget

    Hess Corporation today announced a revised $2.2 billion capital and exploratory budget for 2020, an $800 million reduction from the previous budget of $3.0 billion. The company also announced a new $1.0 billion three year term loan agreement. These actions further strengthen the company’s cash position and financial liquidity in response to the sharp decline in oil prices.
    Full story
  • John Hess Discusses Oil Price Collapse, Company’s Unique Strengths on CNBC’s Fast Money

    CEO John Hess addressed the far-reaching impact of the oil price war on CNBC’s Fast Money on March 12, saying: “The economic problem we're facing today is a lot more than oil, and the oil price crash could be a catalyst that propels the world into an economic recession.”
    Full story
  • Hess Corporation to Give $12.5 Million Gift to the Salk Institute to Accelerate Development of Plant-Based Carbon Capture and Storage

    Salk’s Harnessing Plants Initiative (HPI) will receive a $12.5 million gift from Hess Corporation to advance two projects to enhance plants’ natural ability to store carbon and mitigate the effects of climate change: the CRoPS program and the Coastal Plant Restoration program. These projects build on the Salk discovery of a crucial gene that will help the team develop plants with larger root systems capable of absorbing and storing potentially billions of tons of carbon per year from the atmosphere.
    Full story