Hess in the Media: Hess Confident Stampede on Target for First Oil in 2018
Hess Corporation Logo
SEARCH

Hess in the Media: Hess Confident Stampede on Target for First Oil in 2018

  • Stampede hull arrives at Ingleside, Texas
On Sept. 2, Upstream featured a project update on the Stampede Development, reporting that Hess is confident that the project in the deepwater Gulf of Mexico is on target, as the company works towards first oil in 2018.

“Stampede, sanctioned in 2014, is one of just a handful of standalone US Gulf projects sustaining the local industry amid the oil-price downturn,” the publication noted.
Steve Whitaker, Project Director for Stampede, provided a project update to about 200 members of the Marine Technology Society’s Houston chapter on Aug. 25, on which Upstream based its story.

“From an industry perspective, Hess’ strong commitment to deliver top quartile performance in safety, quality, delivery and cost at the corporate level and on the Stampede project is noteworthy,” said Sandeep Khurana, Senior Manager at Granherne and Director of Programs at the Society, after the presentation. “Hess’ substantive efforts to hold everyone working on the Stampede Project to the company’s high safety standards—from the Hess project sites to those of contractors, as well suppliers and vendors—is particularly significant.”

In the article, the publication said Hess credits close collaboration with contractors such as Kiewit Offshore Services and Heerema Marine Contractors as crucial in staying on track so far.

“We are slightly ahead of schedule,” Upstream quoted Whitaker speaking at the industry event in Houston, while emphasizing early involvement with vendors was important. “That’s made a big difference to us as we have gone through.”

Among several tactics Stampede is leveraging to deliver top quartile performance, Upstream noted that Hess is also applying lessons learned from the start-up of its other recent operated development at the Tubular Bells field, which achieved first oil in 2014.

“A key factor there was the importance of not just construction and delivery but achieving a smooth transition to operations once the taps are turned on,” the article reported. “Hess aims to tackle this challenge by drawing operations staff closer to the project team as well as employing training methods like simulators.

Hess also aims to be particularly vigilant on the cost side, especially given that the project was sanctioned before oil took its precipitous plunge.”

At this stage, Whitaker said, “value erosion is really easy."

Click here to read the article
Latest Hess News
  • Upstream: Hess Checks Off Stampede Installation

    Hess has ticked off another milestone in its progress to first oil at the Stampede development in the US Gulf of Mexico, having completed installation of its tension-leg platform offshore. The US independent also said hookup activities had begun for the development in Green Canyon Blocks 468, 511 and 512.
    Full story
  • Hess’ 2016 Sustainability Report Shows Continued Progress in Safe, Responsible Business Practices

    Hess published its 2016 Sustainability Report, providing a comprehensive review of the company’s strategy and performance on safety, environmental, social and governance programs and initiatives.
    Full story
  • Hess Reports Estimated Results for the 2nd Quarter of 2017

    Hess Corporation reported a net loss of $449 million, or $1.46 per common share, in the second quarter of 2017 compared with a net loss of $392 million, or $1.29 per common share, in the second quarter of 2016, reflecting a lower effective tax rate in 2017 from the required change in deferred tax accounting.
    Full story